NE/2017/07
Contract No. |
NE/2017/07 |
Scope |
The works include construction of the main bridge of CBL and the ancillary viaducts, and implementation of the associated civil, structural, marine, electrical and mechanical, landscaping and environmental protection and mitigation works. |
Commencement Date |
12 July 2018 |
Tentative Completion |
2022 |
Awarded Sum |
Approximate HK$2.5 billion |
Project Office |
East Development Office of Civil Engineering and Development Department |
Consultant |
AECOM Asia Company Limited |
Contractor |
China Road And Bridge Corporation |